Frewin Development Update - 15th May 2023

south walkway.jpgThe paving and garden walling is continuing within the courtyard. The dwarf walls have had copings installed and the initial balustrade posts have been erected. Paving is being laid on the plinth in conjunction with the external lighting.  Work will continue in these areas this week.

The 2nd floor oak slatted ceilings have been completed, except for above stair 2, which is now in progress.

On the south walkway, the paving has been completed to the ground floor and is progressing around stair 1 landing and along the east walkway.

In the bedrooms, final finishes and fixtures are being carried out. Shelving will progress this week courtyard 3.jpgafter the last coat of stain, which was applied on Friday.

Within lower ground, commissioning of the mechanical plant is progressing.