Esocial-kitchen space.jpgxternally, in the courtyard, the edgings and grading of pathways is continuing. Paving will commence this week. Stone walling has been completed round the perimeter.

Internally the main concentration is still continuing along the walkways.

The east walkway oak slatted ceilings have been completed at second floor level.

On the south walkway, the paving has commenced on ground floor south and will progress around this week.

Along the west walkway, cladding has been completed to the first floor and has commenced along the ground floor.

In the bedrooms, final finishes and fixtures are being carried out inc. mirrors. Shelving and ironmongery will progress shortly after the courtyard 2.jpglast coat of stain is applied to the obeche walling. Commissioning and final cleans will be carried out shortly.