Frewin Development Update - 15th February 2023

upper floor bedroom.jpgAll windows are now installed around the courtyard. The bricklayers have completed within the main lightwell, bringing the stonework over the windows and up to paving / cill level.

The glass block walling has been completed with external mastic and the remaining infill blocks installed.

Roof barriers have been installed to separate the pebbles and sedum.

The eighth and final solar thermal frame will be installed this week together with completion of the plumbing connections.

Internally, works are continuing on all floors, with 1st fix virtually completed and solar array install.jpg2nd fix works and decorations progressing.

The bedroom ceilings are being decorated and light fitting installation is following close behind. The engineered oak floors will commence this week, so that the obeche timber walls can progress.

A majority of the en-suite bathrooms are ready for ceramic tiling.

Within lower ground, the limestone tiling is continuing with the feature tiles in the bedrooms. These will complete early this week and then tiling will continue in the east lobby. The timber wall linings have been installed in several of the bedrooms. The ceiling framing and installation in the main kitchen and corridors is in progress and will complete during this week.