Last week the new Velux roof light to the Shoe Lane flat, including the gutter formation and the installation of the fall arrest system were completed externally.
Internally, works continued on all floors with both 1st fix and 2nd fix works progressing.
The electrical wiring has continued out along the corridors, and wiring is being terminated in the various electrical panels in the risers and plantroom.
En-suite bathroom plumbing is continuing to progress well and final boxing in of pipework is also in progress.
Ceramic tiling has just commenced in the first bedroom.
Stannah have commenced the lift installation.
The battening and ceiling construction has also commenced on the second floor
This weeks focus to progress the internal works with around 30 contractors onsite.