Frewin Development Update - 28th November 2022

water tank plantroom.jpgLast week, the high level roof coverings were put on hold to focus on the waterproofing ‘hot melt’ bitumen and felt to be carried out on the lower ground/ground floor. This work not only waterproofs but has enabled the aluminium façade framing to be commenced. These in turn allows the sliding bedroom windows to be fitted.

In addition to these frames, the Velfac window installation has continued with completion of the lower ground windows.

Electrical, ductwork and plumbing works have continued on all floors with water tanks located in the plantroom and underfloor heating pipework installed to the upper floor bedrooms.

Screeding will be carried out to these remaining bedrooms this weekglass wall.jpg

Stannah delivered the lift guides and framing and will commence installation this week.